Dear RESA Community,
For the week of 1/8 the main thoroughfare from upper to lower RE is OPEN.
Below is the breakdown for each day’s water main installation activities:
Monday 1/8 – main thoroughfare open with traffic flaggers
- West Valley Construction will be working from the end of Locust Drive to the intersection of Judith Court/La Verne Drive.
- They will be performing a rolling road closure through out the day, but roads will be open for traffic to pass through.
- Residents should anticipate 2 traffic control flaggers navigating cars around the work.
- Additionally, they will be starting to transfer services from the existing main to the new main. They will start at Naomi court and work their way down.
Tuesday 1/9 – Thursday 1/11 – main thoroughfare open
- WVCC will continue with service transfers the remainder of the week.
- They will cone our work in at each location and do not anticipate any roads to be closed these days.
Sincerely,
RESA Office