SJWC Water Main Installation – Updates for Week of 1/8/24

Dear RESA Community,

For the week of 1/8 the main thoroughfare from upper to lower RE is OPEN.

Below is the breakdown for each day’s water main installation activities:

Monday 1/8 – main thoroughfare open with traffic flaggers

  • West Valley Construction will be working from the end of Locust Drive to the intersection of Judith Court/La Verne Drive.
  • They will be performing a rolling road closure through out the day, but roads will be open for traffic to pass through.
  • Residents should anticipate 2 traffic control flaggers navigating cars around the work.
  • Additionally, they will be starting to transfer services from the existing main to the new main. They will start at Naomi court and work their way down.

Tuesday 1/9 – Thursday 1/11 – main thoroughfare open

  • WVCC will continue with service transfers the remainder of the week.
  • They will cone our work in at each location and do not anticipate any roads to be closed these days. 

Sincerely,
RESA Office