SJWC Water Main Installation – Updates Week of 7/22

Dear RESA Community,

Monday 7/22 & Tuesday 7/23

  • Closure Location: Bayview Drive between Zella Court and Woolaroc Drive.
  • Road Status: Main thoroughfare is OPEN to through traffic utilizing Zella Court as a detour.
  • Resident Access: All residents living within the closure will be able to enter and exit. There may be delays while WVCC crews move/set steel plates to safely get in and out.

Wednesday 7/24

  • Work Area: Bayview Drive between Woolaroc and Dorothy.
  • Closure Locations: 3 locations: (1) intersection of Gloria Court and Bayview Drive, (2) intersection of Bayview Drive and Dorothy Way, and (3) intersection of Woolaroc and Dorothy Way.
  • Detour: A detour route will be implemented via Zella Court.
  • Resident Access: All residents living within the closure will be able to enter and exit.

Thursday 7/25

  • Work Area: Woolaroc Drive between Bayview Drive and Dorothy Way.
  • Closure Locations: 3 locations: (1) intersection of Bayview Drive and Woolaroc Drive, (2) Intersection of Woolaroc Drive and Dorothy Way, and (3) Intersection of Santa Ana Road and Woolaroc Drive.
  • Resident Access: Residents living on Santa Ana Road will be able to exit up towards Summit. Residents living within the closure will be able to enter and exit. 

Sincerely,
RESA Office