SJWC Water Main Installation Updates – Week of 12/16/24

Dear RESA Community,

Next week, the pavement restoration will be working on courts (non-through streets), therefore the main thoroughfare is OPEN.

WVCC will have crews on site at each site below on the following days:

Monday (12/16):

  • No work.

Tuesday (12/17):

  • Mcluckie (Small area in front of the SJW site)
  • Fern Ave from Zella Court to Bayview Drive
  • Gloria Court from end to Bayview Drive

Wednesday (12/18):

  • Santa Ana Road (Lower) from the end to Bayview Drive

Thursday (12/19):

  • NO work.

*Traffic control flagmen will be on site each day to help direct traffic around our work. Residents living on these roads should anticipate delays in entering and exiting the roads/courts when work is being performed. Residents are urged to park outside of the roads to avoid any delays*

Sincerely,
RESA Office