Dear RESA Community,
West Valley Construction Company on behalf of San Jose Water Company will be resuming its water main installation road work beginning the week of 6/2/25.
Summary of road work:
- Monday: roads open with work traffic – main throughfare is open.
- Tuesday & Wednesday: road CLOSED with NO way to get around from 8am-6pm, main throughfare is CLOSED.
- Thursday: road CLOSED with a detour utilizing Zella Court from 8am-6pm, main thoroughfare is OPEN.
Map with color-coded explanations of the work taking place each day below:

Monday 06.02 – RED
- Locations: SJW pump station and across the street from the pump station above Naomi Court. Work will also be taking place at the intersection of Zella Court and Bayview Drive.
- Road NOT Closed: WVCC do not anticipate any hard road closures this day. Residents should anticipate temporary road closures as equipment is being used.
Tuesday 06.03 – ORANGE
- Location: Naomi Court up to “lower Santa Ana Road”.
- ROAD CLOSED: No through traffic will be allowed from 8am-6pm.
Wednesday 06.04 – GREEN
- Locations: from “lower Santa Ana Road” to the intersection of Zella Court and Bayview Drive and up Zella Court, including Eileen Court.
- ROAD CLOSED: No through traffic will be allowed from 8am-6pm.
Thursday 06.05 – BLUE
- Location: from the intersection of Zella Court and Bayview Drive up the road towards the intersection of Bayview Drive and Woolaroc Drive.
- ROAD CLOSED with a DETOUR: There will be a hard road closure at each end of this work area. Detour route will be via Zella Court.
Sincerely,
RESA Office