Below is a schedule for paving the lower portion of the SJWC Water Main Installation Project. Updates for the upper portion of the project (Virdelle/Woolaroc) will be sent out later this week.
For the Week of 5/13, there are closures on the roads below from 8am-6pm.
Monday 05/13
- All of Naomi Court
- Section of Locust Drive to where it meets Santa Ana
- Main thoroughfare is open
Tuesday 05/14
- All of June Court
- Section of Mountain View Court to where it meets Locust Drive
- Section of Locust Drive to where it meets Santa Ana
- Main thoroughfare is open
Wednesday 05/15
- Section of La Verne Drive from the cul-de-sac to where it meets Judith Court
- Main thoroughfare is open.
Thursday 05/16
- Judith Court closed.
- Mountain View Court to Locust Drive closed.
- Locust Drive from Mountain View Court to Santa Ana (hairpin) closed.
- Main thoroughfare is CLOSED.
For the Week of 5/20, there are closures on the roads below from 8am-6pm. There will be no traffic in or out.
Monday 05/20
- Broadway/La Verne Drive from Madrone Drive to Virginia/Beatrice intersection is closed.
- Madrone Drive between the RE Store and Pavilion is closed.
- Main thoroughfare is CLOSED.
Tuesday 05/21
- Broadway/La Verne Drive from Madrone Drive to Virginia/Beatrice intersection is closed.
- Main thoroughfare is CLOSED.
There will be NO crews on site Wednesday 05/22 and Thursday 05/23.