SJWC Water Main Installation Updates Weeks of 5/13 and 5/20 – LOWER Section

Dear RESA Community,

Below is a schedule for paving the lower portion of the SJWC Water Main Installation Project. Updates for the upper portion of the project (Virdelle/Woolaroc) will be sent out later this week.

For the Week of 5/13, there are closures on the roads below from 8am-6pm.

Monday 05/13

  • All of Naomi Court
  • Section of Locust Drive to where it meets Santa Ana
  • Main thoroughfare is open

Tuesday 05/14

  • All of June Court
  • Section of Mountain View Court to where it meets Locust Drive
  • Section of Locust Drive to where it meets Santa Ana
  • Main thoroughfare is open

Wednesday 05/15

  • Section of La Verne Drive from the cul-de-sac to where it meets Judith Court
  • Main thoroughfare is open.

Thursday 05/16

  • Judith Court closed.
  • Mountain View Court to Locust Drive closed.
  • Locust Drive from Mountain View Court to Santa Ana (hairpin) closed.
  • Main thoroughfare is CLOSED.

For the Week of 5/20, there are closures on the roads below from 8am-6pm. There will be no traffic in or out.

Monday 05/20

  • Broadway/La Verne Drive from Madrone Drive to Virginia/Beatrice intersection is closed.
  • Madrone Drive between the RE Store and Pavilion is closed.
  • Main thoroughfare is CLOSED.

Tuesday 05/21

  • Broadway/La Verne Drive from Madrone Drive to Virginia/Beatrice intersection is closed.
  • Main thoroughfare is CLOSED.

There will be NO crews on site Wednesday 05/22 and Thursday 05/23.

Sincerely,
RESA Office

SJWC Water Main Installation Week of 5/6

Dear RESA Community,

The main thoroughfare throughout RE has CLOSURES this week, with detours affecting Virdelle/Woolaroc. See below.

Monday 5/6:

  • Intersection of Locust Drive/Mountain View Court – OPEN with one-way traffic control flaggers
  • Driveway of SJW station on Locust Drive – OPEN with one-way traffic control flaggers
  • Bayview Drive – OPEN, with small crews working
  • Woolaroc/Virdelle Drive going towards Bayview – SECTION CLOSED with detours in place.

Tuesday 5/7:

  • Woolaroc/Virdelle Drive going towards Santa Ana/Woolaroc intersection – SECTION CLOSED with detours in place.

Wednesday 4/8 and Thursday 4/9:

  • Woolaroc Drive from Bayview to Dorothy Way (detour in place) – ROAD CLOSED.
  • Woolaroc Drive between Dorothy Way and Santa Ana – one-way traffic control.
  • Residents living on Santa Ana will be able to exit up Woolaroc towards Summit.

Sincerely,
RESA Office

Week of 4/8 – SJWC Water Main Installation Updates & Office Hours

Dear RESA Community,

SJWC Water Main Installation

There is no work for the project this week, therefore there are NO road closures for the week of 4/8.

Office Hours

There will be NO office hours this week. They will resume week of Monday 4/15. We apologize for the inconvenience.

The RESA Office will still available via email and phone (408) 353-1866 Mon-Fri from 8am-5pm next week.

Sincerely,

RESA Office

SJWC Water Main Installation – Updates Week of 3/25

Dear RESA Community,

Here are the SJWC water main installation updates for the upcoming week:

Monday 3/25 – Tuesday 3/26

  • Road Status: OPEN with traffic control
  • Work Location: 21551 Santa Ana Road

Wednesday 3/27

  • Road Status: OPEN with traffic control

Thursday 3/28

  • Water Shutdown: residents affected will be notified via door hanger on Tues 3/26
  • Road Status: OPEN with traffic control
  • Work/Shutdown Location: intersection of Santa Ana Road and Lenore Court

Sincerely,
RESA Office