SJWC Water Main Installation – Update Week of 11/13

Dear RESA Community,

The main thoroughfare from upper to lower Redwood Estates is Monday & Tuesday this week, but with one-way traffic control and detours, listed below.

The main thoroughfare is CLOSED on Wednesday & Thursday. All closures effective 8am-6pm.

Below is the plan for both sections of the project:

Upper Section:

  • Monday (11/13)
    • West Valley Construction Co. (WVCC) will have a small crew working to clean up and prepare for rain.
  • Tuesday (11/14)
    • WVCC will be working at the San Jose Water station. They will be able to flag one way traffic at this location. 
  • Wednesday (11/15)
    • West Valley Construction Co will need to close the road to through traffic from June Court to Naomi Court.
    • There will be a traffic control flagger at each closure helping direct people to the open exit route.
    • Anticipate a small 2-man crew performing saw cutting work at the intersection of La Verne Drive / Judith Court and Locust Drive / Mountain View Court. This will be minimal work that will take place during the morning hours. 
  • Thursday (11/16)
    • Upper Section: CLOSED to through traffic
    • Location 1: the intersection of Mountain View Court/ Locust Drive
    • Location 2: the intersection of Judith Court/La Verne Drive.
    • The road will be closed to thru traffic at June Court and at Judith Court/La Verne Drive.
    • Residents that live down Mountain View Court and La Verne Drive should anticipate work activity. WVCC will do our best to get residents out of these roads if needed. 

Lower Section:

  • Monday (11/13)
    • WVCC will be continuing to install new water main from Mary Alice Way towards Laurel Drive.
    • Madrone Drive will be closed to thru traffic.
    • Residents living on Mary Alice Way will be able to exit up towards the general store.
    • The flagged detour will take you around Laurel Drive, Redwood Drive, and Madrone, emptying out at Nonno’s.
  • Tuesday (11/14)
    • WVCC will be continuing to install new water main towards the Pavilion.
    • Madrone Drive will be closed to thru traffic from Mary Alice Way to the Pavilion entrance.
    • Residents living on Mary Alice Way will be able to exit up towards the general store.
    • The flagged detour will take you around Oak Drive, Laurel Drive, and Madrone, emptying out at Nonno’s.
  • Wednesday (11/15)
    • WVCC will be falling back to install new fire hydrants along Madrone Drive to the RE Store.
    • The road will be closed to thru traffic from Mary Alice Way to the RE Store.
    • Residents living on Mary Alice Way will be able to exit down towards the Pavilion. 
    • The flagged detour will take you around Laurel Drive, Redwood Drive, and Madrone, emptying out at Nonno’s.
  • Thursday (11/16)
    • West Valley Construction Co. will be working on installing a hydrant located just below the RE store in front of address 21400 Madrone Drive.
    • Madrone Drive will be open to through traffic: there will be traffic control flaggers to flag any traffic around the work. No detour will be implemented.

Sincerely,
RESA Office

Road Updates Week of 11/6

Dear RESA Community,

SJWC Water Main Installation

The main thoroughfare from upper to lower Redwood Estates is OPEN this week, but with one-way traffic control and detours, listed below. All closures effective 8am-6pm.

Here are more details of the closures:

Upper SectionThis section is not fully closed, but there will be traffic in and out.

  • Monday (11/06) and Tuesday (11/07)
    • Minor construction activity at the intersection of La Verne and Judith Court throughout each day. Anticipate water trucks and work trucks around this area. You may encounter a water truck blocking the road while it is being filled up. It will only be temporary. WVCC will work with residents who need to get pass our work. 
  • Wednesday (11/08) and Thursday (11/09)
    • WVCC crew will be working at the San Jose Water station. No roads will be affected these two days. Residents should expect work truck traffic.

Lower Section: This section is not fully closed; it is accessible via a detour and traffic control, map at the bottom.

  • Monday (11/06) thru Thursday (11/09)
    • Installation will occur from the RE store towards Mary Alice Way. Madrone Drive will be closed to thru traffic from the general store to the intersection of Madrone Drive and Laurel Drive Monday – Thursday 8am to 6pm next week.
    • A detour will be implemented around the work area utilizing Laurel Drive/Redwood Drive/Madrone Drive. Traffic control contractor will set up 5 flaggers at specific locations along this detour to safely flag one way traffic through this detour.
    • Residents living in our work area throughout next week are urged to park their vehicle outside of the work area to avoid any delays when trying to enter or exit their residence.
    • Residents that live on Mary Alice will be able to exit down Madrone towards the Pavilion.

Storm 2022-2023 Road Repairs

As you know, RESA is working with FEMA, SCC, Cal OES, the SBA, and various contractors in road repair efforts. In the following months, please note that state/federal agencies, contractors, etc. may make visits to our storm damaged roadways. If you see any of these representatives, please do not be alarmed and allow them to continue their work in moving the road repair process along.

Sincerely,
RESA Office

SJWC Water Main Installation – Updates Week of 10/30

Dear RESA Community,

ON MONDAY, the main thoroughfare from upper to lower Redwood Estates is OPEN.

TUESDAY – THURSDAY, the main thoroughfare from upper to lower Redwood Estates is NOT OPEN.

All closures effective 8am-6pm.

UPPER SECTIONThis section of the road is not fully closed on any day this week – through traffic is permitted.

  • Monday (10/30)
    • Minor activity at the intersection of La Verne and Judith Court and in the San Jose Water Station. The road is not fully closed at this location on this day.
  • Tuesday (10/31)
    • Minor activity at the intersection of La Verne and Judith Court and in the San Jose Water Station. The road is not fully closed at this location on this day.
  • Wednesday (11/1)
    • WVCC will be loading the new main with water at the SJWC Water Station. The road is not fully closed at this location on this day, just high truck traffic.
  • Thursday (11/2)
    • WVCC will be pressure testing the new main at the SJWC Water Station. The road is not fully closed at this location on this day, just high truck traffic.

Lower Section: This section of the road with have flagged 1-way traffic control on Monday allowing through traffic, but will be FULLY CLOSED Tues-Thurs.

  • Monday (10/30)
    • WVCC will be potholing several locations along the lower section of the project. They will take place along Broadway Road and Madrone Drive. All areas they are working will be able to utilize subcontracted traffic control and flag 1 way traffic around the work.
  • Tuesday (10/31)
    • Water main installation is taking place, road closed at Virginia Drive and Idalyn Drive. Residents who live on Virginia Drive will be able to exit via Summit. Residents who live on Idalyn Drive will be able to exit towards the Pavilion.
  • Wednesday (11/1)
    • Road closed from Idalyn Drive to ~ the RE Store. Residents who live on Idalyn Drive and above will need to exit via Summit Rd. Below is a map of the closure work. 
  • Thursday (11/2)
    • We will be closing the road from ~ the RE Store to address 21404 Madrone Drive. Below is a map of work. 

SJWC Water Main Installation – Updates Week of 10/23

Dear RESA Community,

For all dates below, the main thoroughfare from upper to lower Redwood Estates is NOT open.

All road closure dates are effective 8am-6pm.

Monday 10/23

  • The installation of water main will continue down Judith Court. The road will be closed to thru traffic from Locust Drive/Mountain View Court to La Verne Drive/Judith Court.
  • Residents that live down La Verne Drive and Patricia Court will be affected by the road closure, as we will be trenching across the entrance to the road towards the already installed main.

Tuesday 10/24

  • WVCC will be working on Installing Services at address 18096 Mountain View Court and 18097 Mountain View Court.
  • Once these services are installed, they will move up to address 21536 and 21550 Locust Drive to installed new services.
  • For the houses on Mountain View Court the road will be closed at Mountain View Court/Locust Drive and at Mountain View Court/ Judith Court.
  • Once those are completed, we will move the closure up to the two addresses on Locust Drive.
  • The road closure for these will be at June Court/Locust Drive and Locust Drive/The San Jose Water Station Driveway Entrance.

Wednesday 10/25 and Thursday 10/26

  • WVCC will be working around the San Jose Water Station. The road will be closed From June Court to Naomi Court. This is the same road closure we had the last few weeks.

Sincerely,
RESA Office

SJWC Water Main Installation – Updates for Week of 10/16

Dear RESA Community,

The main thoroughfare from upper to lower Redwood Estates is NOT OPEN Mon-Thurs this week.

Below are the areas of work effective 8am-6pm:

  • Monday 10/16
    • WVCC will be working on June Court and Locust Drive from Naomi Court to June Court. Locust Drive will be closed just before June Court to Naomi Court. They will work on getting residents on Locust Drive out safely.
  • Tuesday 10/17
    • WVCC will be working on installing main from June Court to Mountain View Court. Mountain View court will be closed on this day.
  • Wednesday 10/18
    • WVCC will be working from Mountain View Court down towards Judith Court. They will work on allowing an entrance and exit lane for residents living on Mountain View Court.
  • Thursday 10/19
    • WVCC will continue installing main down Locust Drive towards Judith Court.

We appreciate your patience in this matter.

Sincerely,
RESA Office