SJWC Water Main Installation – Project Updates Week of 7/5

Dear RESA Community,

The following maps and descriptions are for the road closures for Wednesday 7/5, Thursday 7/6, and Mon 7/10:

Mountain View Ct, La Verne Dr, Judith Ct, Patricia Ct.

The following map and description will be from Mon 7/10 – Thurs 7/13, keeping Locust Drive closed down the hill:

Mountain View Ct, La Verne Dr, Judith Ct, Patricia Ct.

A Note from West Valley Construction:

Access will be closed (limited to emergency access) in the red areas; the main vein being Locust Dr all the way down to La Verne. This would mean that residents located above the closure will need to enter and exit via the back way on Summit Rd. Those below the red area would need to enter and exit down Broadway Rd.

We understand this is going to potentially cause some frustration not having the access up and down the hill by way of Locust Dr, but hopefully this map helps you plan and detour different directions depending on where they are located.

WVCC will follow up regardless on Wednesday afternoon with an update so we can keep the days, locations, and durations as clean as possible moving forward.

Sincerely,
RESA Office

SJWC Water Main Installation – Mt View Ct

Dear RESA Community,

Below is an update regarding WVC’s newest site of work for the SJWC Water Main Installation:

Wed 6/28 (starting mid-morning) – Thurs 6/29: Mt. View Ct starting at Locust Dr. proceeding to the end of Mt. View Ct. will be closed — there is a possibility there will still be work on Friday, depending upon progress on Wed-Thurs.

We appreciate everyone’s patience as we work through this project as quickly and efficiently as possible. We will work to get you more advanced notice in the updates to come.

Map

SJWC Water Main Installation – Locust Drive

Here are project updates on the SJWC Water Main Installation:

Previous Work

  • Staking has been initiated on La Verne Drive to Judith Court.

Upcoming Work

  • Tues 6/20: They will be mobilizing smaller pieces of equipment. Surveyors will continue staking from their progress last week.
  • Wed 6/21-Wed 6/28: They will be potholing on La Verne Drive – they will start at the end of the court and work out towards Judith Court.

Closures

  • Wed 6/21: La Verne from Patricia Ct. to the end of La Verne will be closed
  • Thurs 6/22 & Mon 6/26-Thurs 6/29: La Verne from Judith Court to the end of La Verne Drive will be closed.

Map

SJWC Water Main Installation

Greetings Residents of Redwood Estates,

West Valley Construction, on behalf of San Jose Water Company, will be installing a new water main and services on the following streets: Madrone Drive (Pavilion to R.E. Store), Broadway Rd., Laverne Dr., Patricia Ct., Judith Ct., Mt. View Ct., and Locust Ct. beginning on or near June 5th


Utility owners will mark the location of existing underground utilities with white markings. We will begin potholing to dig down and verify the depth and location of any utilities that may be present. All trenches and potholes will be backfilled or covered with steel trench plates at the end of each day.

This process will take several weeks to complete. We will send out a map showing our starting location with highlighted roads that will be affected to allow residents/business owners to plan accordingly. Access in-and-out of your homes will be granted as needed – for narrow roads, there will be times during the day that certain areas are not accessible.

The project work hours are limited to 8AM-6PM Monday through Thursday. We appreciate your cooperation and understanding.

Water services will not be interrupted during the installation process over the next several months. However, once this project is near completion, and the new water main is activated, we will need to switch your water service connection to the new water main. This process will require your water services be turned off for a period of 6-8 hours. Residents affected by this new water main connection will be notified at least 72-hours before the interruption.


Please, be on the lookout for updates in the coming weeks as we look forward to getting this project underway.

Thank you,
Ryan Marten
West Valley Construction Company                             

Pavilion parking lot demolition & construction

The Pavilion parking lot is scheduled for demolition and re-construction beginning tomorrow March 7th at 8:00 am, lasting approximately 10-days.

Parking will be extremely limited, if not completely unavailable, Mon-Fri from 7:00am-4:00pm, until the project is complete.

We apologize for any inconvenience.

Thank you,
RESA Office Staff