Below is the breakdown for each day’s water main installation activities:

Monday 1/15

  • No crew on site for the MLK Holiday.

Tuesday 1/16 & Wednesday 1/17

  • No roads will be closed.
  • Anticipate work truck traffic on Mountain View Court and La Verne – service transfers will be occurring.

Thursday 1/18

  • Traffic control flaggers will flag one way traffic around work near Naomi Court.