SJWC Water Main Installation – Updates Week of 9/16

Dear RESA Community,

The main thoroughfare in Redwood Estates is open. Hours are 8am-6pm

Monday 9/16:

  • Site 1
    • Work Location: McLuckie
    • Road Status: WVCC urges residents living on this street to park off of the road to avoid delays.
  • Site 2
    • Work Location: Zella Court from its intersection with Bayview to 18187 Zella Court.
    • Road Status: Road is closed to through traffic, residents living on Zella will be able to exit towards Fern Avenue.

Tuesday 9/17:

  • Site 1
    • Work Location: Gloria Court
    • Road Status: Residents with driveways on Gloria Court are urged to park out of the court to avoid any delays. 
  • Site 2 (same as Monday)
    • Work Location: Zella Court from its intersection with Bayview to 18187 Zella Court.
    • Road Status: Road is closed to through traffic, residents living on Zella will be able to exit towards Fern Avenue.

Wednesday 09/18:

  • Site 1
    • Work Location: Zella Court from its intersection with Bayview to 18187 Zella Court.
    • Road Status: Road is closed to through traffic, residents living on Zella will be able to exit towards Fern Avenue.
  • Site 2
    • Work Location: Gloria Court
    • Road Status: Residents with driveways on Gloria Court are urged to park out of the court to avoid any delays. 
  • Site 3
    • Work Location: Intersection of Woolaroc and Dorothy.
    • Road Status: Open with one-way traffic flaggers around the work.
  • Site 4
    • Work Location: Intersection of Woolaroc and Virdelle.
    • Road Status: Open with one-way traffic flaggers around work.

Thursday 09/19:

  • Same as Wednesday, minus work Site 3.

Sincerely,