SJWC Water Main Installation Updates for Week of 5/13 – UPPER Section

Dear RESA Community,

For the week of 5/13, there is work taking place from 8am-6pm. WVCC will accommodate residents living on these streets to get in and out of their homes. Due to the work being performed, there may be a delay, so please allow extra time for your transit.

On all days, the main thoroughfare is OPEN, with detours around work sites.

Monday 5/13:

  • ROLLING CLOSURE: only one of the streets below will be closed at a time. If one is closed, the other section will be open to allow traffic around work.
  • Woolaroc CLOSED first, once their work is done here, they will move onto…
  • Section of Bayview between Dorothy/Fern and Woolaroc CLOSED after the section mentioned above.

Tuesday 5/14:

  • Section of Bayview between Dorothy/Fern and Woolaroc CLOSED all day.
  • Traffic will be detoured around the work will be in place, using Woolaroc and Dorothy.

Wednesday 5/15:

  • ROLLING CLOSURE: only sections of the road will be closed at a time, allowing traffic around the work sites.
  • Sections of Woolaroc Drive will be closed at a given time. They will be starting at Virdelle, making their way towards Bayview.
  • Residents on Santa Ana will be able to enter/exit, but there may be delays, please allow extra time for your transit.

Thursday 5/16:

  • Section of Bayview from Woolaroc to Gloria will be closed all day.
  • Detour signage in place utilizing Zella.

Updates above are for the portion of the project that is in upper Redwood Estates. The road paving taking place on Naomi, Judith, Mountain View, Locust, La Verne is still taking place. Please see the previous email for those road closures: https://conta.cc/44AtFG3

Below is a map of the closure sites: