SJWC Water Main Installation – Updates for Week of 1/29

Dear RESA Community,

For the week of 1/29 the main thoroughfare from upper to lower RE is OPEN.

Below is the breakdown for each day’s water main installation activities:

Monday 1/29

  • Road Status: OPEN with two-way flaggers directing traffic around work sites.
  • Work Areas: crew one at La Verne & Judith, crew two at Locust just above Mountain View Court.

Tuesday 1/30

  • Road Status: OPEN with two-way flaggers directing traffic around work sites.
  • Work Areas: same as Monday.
  • WATER SHUTDOWN: residents affected were notified Friday 1/26 via door hanger.

Wednesday 1/31

  • No work scheduled.

Thursday 2/1

  • No work scheduled.

Sincerely,
RESA Office

SJWC Water Main Installation – Updates Week of 1/22

Dear RESA Community,

For the week of 1/22 the main thoroughfare from upper to lower RE is OPEN.

Below is the breakdown for each day’s water main installation activities:

Monday 1/22

  • Roads OPEN. No crews on site due to forecast. Subject to change.

Tuesday 1/23

  • Work Location: near Naomi Ct & Locust Drive (SJWC Water Station).
  • Road Status: work truck traffic, no roads closed.

Wednesday 1/24

  • NO crews on site due to forecasted weather.
  • Rescheduled for Tuesday 1/30.

Thursday 1/25

  • TBD – Plan will be provided later on next week.

Sincerely,
RESA Office

SJWC Water Main Installation – Updates Week of 1/15/24

Dear RESA Community,

For the week of 1/15 the main thoroughfare from upper to lower RE is OPEN.

Below is the breakdown for each day’s water main installation activities:

Monday 1/15

  • No crew on site for the MLK Holiday.

Tuesday 1/16 & Wednesday 1/17

  • No roads will be closed.
  • Anticipate work truck traffic on Mountain View Court and La Verne – service transfers will be occurring.

Thursday 1/18

  • Traffic control flaggers will flag one way traffic around work near Naomi Court.

Sincerely,
RESA Office

SJWC Water Main Installation – Updates for Week of 1/8/24

Dear RESA Community,

For the week of 1/8 the main thoroughfare from upper to lower RE is OPEN.

Below is the breakdown for each day’s water main installation activities:

Monday 1/8 – main thoroughfare open with traffic flaggers

  • West Valley Construction will be working from the end of Locust Drive to the intersection of Judith Court/La Verne Drive.
  • They will be performing a rolling road closure through out the day, but roads will be open for traffic to pass through.
  • Residents should anticipate 2 traffic control flaggers navigating cars around the work.
  • Additionally, they will be starting to transfer services from the existing main to the new main. They will start at Naomi court and work their way down.

Tuesday 1/9 – Thursday 1/11 – main thoroughfare open

  • WVCC will continue with service transfers the remainder of the week.
  • They will cone our work in at each location and do not anticipate any roads to be closed these days. 

Sincerely,